Obrenovac-Surčin Bridge (A2 motorway)

Coordinates: 44°39′58″N 20°14′48″E / 44.666060°N 20.246721°E / 44.666060; 20.246721
From Wikipedia, the free encyclopedia
Obrenovac-Surčin Bridge
Coordinates44°39′58″N 20°14′48″E / 44.666060°N 20.246721°E / 44.666060; 20.246721
Carries6 lanes of A2 motorway
CrossesKolubara and Sava rivers
LocaleMunicipalities of Obrenovac and Surčin
City of Belgrade, Serbia
Other name(s)Мост Обреновац-Сурчин
Most Obrenovac-Surčin
Maintained byPutevi Srbije
Characteristics
Total length1.7 km (1.1 mi)
History
Construction startFebruary 12, 2017; 7 years ago (2017-02-12)
OpenedDecember 17, 2019; 4 years ago (2019-12-17)
Location
Map

The Obrenovac-Surčin Bridge on A2 motorway (Serbian: Мост Обреновац-Сурчин, romanizedMost Obrenovac-Surčin) is the bridge crossing the rivers Kolubara and Sava in the suburban section of Belgrade, the capital of Serbia. It is part of the A2 motorway, in Serbia more often called Corridor XI. Preparatory works on the bridge began on 12 February 2017 and it was ceremonially opened, with the adjoining Obrenovac-Surčin section of the motorway, on 17 December 2019.

Location[edit]

On Obrenovac side, the bridge is located west of the town itself and just north of Barič. On Surčin side, it crosses into the uninhabited area of Boljevci, southeast of the village.[1]

Construction[edit]

Preparatory works began on 12 February 2017.[2] Ceremony marking the official beginning of the construction, attended by the Minister of Construction, Zorana Mihajlović, was held on 23 May 2017. The construction of the 17.6 km (10.9 mi) long Surčin-Obrenovac section of the A2 motorway began on 1 March 2017, and both the motorway and the bridge, should be finished by the end of 2019.[3]

By August 2017 all 252 piles projected on the ground section were finished and the construction of the piles for the main beam across the Sava, from the Obrenovac direction, began. Construction of the body of the bridge should began by the end of 2017.[4]

In October 2018 it was announced that the bridge will be open for the pedestrians in April–May 2019. The opening of the completely finished bridge was set for 5 January 2020.[5] It was also stated that the Surčin-Obrenovac motorway itself, without which the bridge has no purpose, will be finished by the end of 2020 or early 2021, and not at the beginning of 2020, as previously stated. Beginning of the construction of the final, 9 km (5.6 mi) long Surčin-New Belgrade section, which will connect the motorway and the bridge directly with Belgrade, was announced for 2019.[6] Works didn't start, and in December 2020, the beginning of the works was announced for March 2021.[7]

The construction company which builds the bridge is the CCCC, China Communications Construction.[3][4]

In August 2019, section of the A2 motorway below Obrenovac was opened for traffic and named "Miloš Veliki". Section of the motorway which should connect the bridge to it, on both sides, wasn't finished and after numerous changes it was announced that the new price will be €9 million per km, which is deemed way to much by the experts, as the road is being constructed in the low, flat, non-urbanized area. As the access to the opened section of the motorway from the Belgrade direction wasn't done properly, this caused traffic collapses and 10 km (6.2 mi) long traffic jams. Authorities claim that the traffic will be relieved when the remaining part of the motorway, including the bridge, will be finished and functional, by the end of 2019.[8][9][10]

The bridge was ceremonially opened on 17 December 2019, jointly with the adjoining section of the Obrenovac-Surčin motorway. That way, the bridge was connected with the motorways on both sides. Despite the claims that the construction of the access roads was without any problems, the fact that the terrain was easy for the construction and that work was finished almost a month before deadline, the total price of the bridge motorway grew to €12 million per km in the end.[11]

The direct connection to New Belgrade finally began on 31 March 2021. The 7.9 km (4.9 mi) long "motorway which will not be a classical motorway" with reduced speed to 80 km/h (50 mph) was to be finished in September 2022, but was opened on 1 April 2023. Despite easy terrain, the total cost remained high, $70.5 million, or $9 million per kilometer due to the claimed "specific thoroughfare" which needed "special technology of construction".[12]

Characteristics[edit]

The length of the bridge, which spans two rivers, Kolubara (near its mouth into the Sava) and Sava, was variously reported as 1,581 m (5,187 ft),[3] 1,700 m (5,600 ft)[4] and 1.800 m (5 ft 10.9 in).[2] 84,000 m3 (3,000,000 cu ft) of concrete will be built into the bridge.[3]

References[edit]

  1. ^ Turističko područje Beograda. Geokarta. 2007. ISBN 978-86-459-0099-2.
  2. ^ a b A.R. (12 February 2017). "Novi most preko Save: Priprema se teren za gradilište u Obrenovcu" (in Serbian). Blic.
  3. ^ a b c d Tanjug (23 May 2017). "Počela gradnja novog mosta preko Kolubare i Save" (in Serbian). Radio Television Serbia.
  4. ^ a b c Dejan Aleksić (11 August 2017), "Novi most preko Save kod Obrenovca po planu", Politika (in Serbian), p. 15
  5. ^ Dejan Aleksić (18 October 2018). "Preko Save i Kolubare pešice na proleće" [Across the Sava and the Kolubara on foot in spring]. Politika (in Serbian). p. 15.
  6. ^ Dejan Aleksić (25 October 2018). "Почетак изградње ауто-пута најављен ѕа идућу годину" [Beginning of the motorway construction announced for the next year]. Politika (in Serbian). p. 15.
  7. ^ Градња деонице Нови Београд-Сурчин почиње у марту [Construction of the New Beograd-Surčin section starts in March]. Politika (in Serbian). 24 December 2020. p. 10.
  8. ^ Mladen Savatović (21 August 2019). "Cena deonice autoputa od Novog Beograda do Surčina skočila u odnosu na najave" [Price of the New Belgrade-Surčin section of the motorway jumped high compared to the promised one]. N1 (in Serbian).
  9. ^ M. N. Stevanović (22 August 2019). "Devet miliona evra po kilometru, neobjašnjiva cena auto-puta do Surčina" [Nine million Euros per kilometer, inexplicable price of the Surčin motorway]. Danas (in Serbian).
  10. ^ Beta (23 August 2019). "Saobraćajni kolaps na putu Beograd-Obrenovac zbog uključenja na novi autoput" [Traffic collapse on the Belgrade-Obrenovac road because of the access to the new motorway]. N1 (in Serbian).
  11. ^ Dejan Aleksić (18 December 2019). Аутомобили од данас на ауто-путу Обреновац-Сурчин [Automobiles on the Obrenovac-Surčin motorway from today]. Politika (in Serbian). p. 15.
  12. ^ Dejan Aleksić (1 April 2023). Нови Београд–Сурчин од вечерас у саобраћају [New Belgrade-Surčin opens for traffic tonight]. Politika (in Serbian). p. 13.